Completed Projects



C.C. Lining work in Ganga canal Division of Bulandshahr & Aligarh under THDC Pariyojana Us
Department U.P. Irrigation Department
Nature of Work C.C. Work
Year 2019-2023
Work Cost (in Crore) 147.00 Cr.
Value in USD ( in Million) 17.18 Million
Balance Work of Hajipur- Muzaffarpur Bypass Four Lane Road Work of NH77
Department NHAI
Nature of Work Road Work
Year 2020-2022
Work Cost (in Crore) 250.00 Cr
Value in USD ( in Million) 29.22 Million
Restoration of Hardoi Br. At Km. 159.291 to 251.093
Department U.P. Irrigation Department
Nature of Work Earth Work
Year 2018-2019
Work Cost (in Crore) 16.58 Cr.
Value in USD ( in Million) 1.93 Million
Cleaning of Silt in Hardoi Canal from Km. 0.000 to 21.600
Department U.P. Irrigation Department
Nature of Work Earth Work
Year 2016-2017
Work Cost (in Crore) 9.77 Cr
Value in USD ( in Million) 1.14 Million
E/W in Restoration of Gonda Branch (Km 0.000 to 120.600) (Earth Work)
Department U.P. Irrigation Department
Nature of Work Earth Work
Year 2016-2017
Work Cost (in Crore) 36.97 Cr.
Value in USD ( in Million) 4.32 Million
Greenfield Connectivity for Jewar International Airport Link Road km.16 to km.32
Department APCO INFRA PVT LTD
Nature of Work Road Work
Year 2023-2024
Work Cost (in Crore) 257.00 Cr.
Value in USD ( in Million) 30.04 Million
Construction of Minor Bridge, VUP & Box Culverts from Ch. 00+787 to Ch. 6+987 of Mathura Bypass (Pkg-1B) Project
Department PNC INFRATECH LTD
Nature of Work Road Work
Year 2023-2024
Work Cost (in Crore) 115.00 Cr.
Value in USD ( in Million) 13.44 Million
Pellet Plant - Iron Ore Beneficiation / 10 Lakh Metric Ton PA/ 10 Lakh Metric Ton PA
Department Govt. of Chhattisgarh
Nature of Work Industry
Year 2023
Work Cost (in Crore) 499.99 Cr
Value in USD ( in Million) 58.45 Million
Rehablitation & Upgradation of Two laning of Maheshkunt-Saharsa-Purnia of NH-107
Department NHAI
Nature of Work Road Work
Year 2020-2022
Work Cost (in Crore) 180 Cr.
Value in USD ( in Million) 21.04 Million
Hardoi Branch Restoration of earth on silt and clearance.
Department Irregation Department
Nature of Work Silt And Clearance.
Year 2018-2019
Work Cost (in Crore) 15.00 Cr
Value in USD ( in Million) 1.75 Million
Hardoi Branch Restoration of earth on silt clearance.
Department Irregation Department
Nature of Work Silt And Clearance.
Year 2018-2019
Work Cost (in Crore) 14.00 Cr.
Value in USD ( in Million) 1.63 Million
Earth Work Bank strengtheing and improvement of internal section of Sarda Sahayak canal
Department EE Flood Works
Nature of Work Earth Work
Year 2015-2015
Work Cost (in Crore) 60 Cr.
Value in USD ( in Million) 7.01 Million
C.C. Lining work of Tanda Pump Canal
Department Irrigation Department
Nature of Work C.C. Lining work
Year 2015-2020
Work Cost (in Crore) 150.00 Cr.
Value in USD ( in Million) 17.53 Million
Construction of Jarmar left Canal (Aggrement canal crossing, super passage etc.)
Department EE Irrigation
Nature of Work Construction
Year 2015-2017
Work Cost (in Crore) 28.00 Cr.
Value in USD ( in Million) 3.27 Million
Earth work in construction of left main canal including all pucca work & right main canal of lower Rohini Dam.
Department EE Irrigation
Nature of Work Earth work
Year 2013-2014
Work Cost (in Crore) 23.00 Cr
Value in USD ( in Million) 2.68 Million